Balfour Beatty VINCI (BBV) has begun installing precast concrete deck slabs on the five interconnected viaducts that form the final mile of HS2’s Curzon approaches into Birmingham, as reported by Rail Technology Magazine. A 125-tonne gantry crane positioned above the Lawley Middleway viaduct will start an 18-month programme of slab installation, moving on to Curzon 2, Curzon 1 and finally Duddeston Junction.
BBV is the main works contractor for HS2’s West Midlands section. The slabs are manufactured at BBV’s purpose-built Kingsbury factory in Warwickshire, whose 140-strong workforce spent four years producing 2,742 segments for the Delta Junction viaducts before switching to the precision-designed deck slabs, according to New Civil Engineer.
The 55,000m² Kingsbury site employed more than 500 people at its peak and runs an on-site Skills Academy, as reported by New Civil Engineer. Balfour Beatty VINCI has stated that the yard will produce over 1,200 deck slabs for the Curzon viaducts using the same experienced team.
The slabs are laid one at a time above the road and public walkways, so installation over Lawley Middleway requires temporary overnight road closures between Garrison Circus and Curzon Circus, as stated by Rail Advent.
BBV section manager Malik Kayatas said, according to Rail UK: “A 125-tonne gantry crane will begin installing deck slabs along a series of interconnected viaducts in Birmingham this week.”
The Kingsbury yard cast the Delta Junction segments, each weighing up to 85 tonnes, for a triangular network of viaducts carrying the line over motorways, roads, railways, rivers and floodplains outside Birmingham, as reported by New Civil Engineer.
The structural driver is deck installation sequencing across interconnected viaducts, where the crane must be ready at each structure as work moves along the route.
For the sector, the switch from segment production to slab manufacture keeps a 140-strong factory team in work while the final viaduct decks are completed ahead of track installation.